New School Construction Update

This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.

The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.

Similar Posts

  • Latest New School Construction Update

    Next week (December 17 to December 21), material and equipment deliveries and installation work will continue on all floors inside the building.

    The following week (December 24 to December 28), Material and equipment deliveries and installation work will continue on all floors. The site will be closed on December 25th for the holiday but will be open on Monday the 24th and Wednesday the 26th.

    This weekend the site will be open on Saturday, December 15th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Filene’s Space to Become Burlington Coat Factory

    Burlington Coat Factory, a leading national off-price retail chain, has announced today that it will open a new flagship store in the space formerly occupied by Filene’s. Burlington offers brand name merchandise for the entire family and home with up to 65% off department store prices every day. The new location will feature the latest trends in ladies’ dresses, suits, sportswear, juniors, accessories, menswear, family footwear and children’s clothing. It will also include a broad assortment of furniture and accessories for baby at Baby Depot, home decor and gifts, along with the largest selection of coats in the nation.

  • Latest New School Construction Update

    Next week (April 1 to April 5), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. We will be work on the new sidewalks around the building as well.

    The following week (April 8 to April 12), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. By then end of this week we plan to have the rest of the sidewalk on 14th street complete. Additionally we plan to begin removing the sidewalk shed along 5th ave.

    This weekend the site will be open on Saturday, March 30th for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Korean War?

    Here on 13th St., ten-year-old Korean restaurant DoSirak has closed, while across the street in our building, BAK has opened. As it turns out, the BAK folks are the DoSirak folks, so all is well. Kimchi for all.