Latest Construction Update: More of the Same

From The New School:

Next week (September 19 to September 23), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls around the perimeter of the site and slab on grade work will continue. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. DOT approved street connections to underground utilities on Fifth Avenue will progress. A small cherry picker crane will arrive on site next week, and be stationed inside the Fifth Avenue fence. This crane will remain on site for approximately two months.

The following week (September 26 to September 30 ), we will continue with concrete foundation walls and slabs, line drilling, rock excavation, loading out, interior core foundation work, street utility connections on Fifth Avenue, and underground electrical and plumbing.

DEP continues to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

The site will be open on Saturday, September 17th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork, plumbing and electrical work, site utility connections, waterproofing and rebar for concrete placement, and the installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

Similar Posts

  • Latest Construction Update from The New School

    Next week (August 22 to August 26), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 29 to September 3 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street.

  • The Neighborhood Commerical Real Estate Update

    The Union Square Partnership Business and Broker Report for the 1st quarter updates us on what’s new and pulsating in the neighborhood.

    Union Square has started the year off on a high note with 10 new business openings and foot traffic recovering to 99% of 2019 levels, a 4% increase from the last quarter. Newcomers include a range of quick service eateries and high-profile sit down establishments, such as the new Coastal Indian
    restaurant Kanyakumari from well-regarded Fungi Hospitality. Popular mattress retailer Saatva joined the established home goods corridor on Broadway, and Sweet Cats Cafe brings more family-friendly entertainment to the neighborhood.

  • Latest New School Construction Update

    Next week (March 19 to March 23), Superstructure work will continue at the 8th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (March 26 to March 30), we will continue superstructure concrete and slabs on the 8th and 9th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    This weekend the site will be open on Saturday, March 17th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

    In addition, tomorrow, Friday the 16th, we will be starting operations at 6am in anticipation of a large concrete pour and will more than likely, with notification of the Department of Buildings, be going later into the evening to finish. Also on the weekend of the 10th the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.

  • NYPD 6th Precinct Community Council Meeting–September 25

    The NYPD 6th Precinct Community Council Meeting will take place in person Wednesday, September 25 at 7:00 PM

    Our Lady of Pompeii’s Fr. Demo Hall – Lower Level at the corner of Bleecker and Carmine Streets

    note: meeting will begin promptly at 7:00 pm 

    Please sign in at the door early if you wish to speak or ask questions of the panel.

    Join the leadership of the 6th Precinct, your neighbors and local businesses for an update on community affairs.  This is also your opportunity to advise Precinct Leadership of chronic or specific crime/safety/quality of life problems you see in our community so their actions are directed with your unique insights. Take this opportunity to listen or to voice your thoughts in an open and informative session.  We encourage you to tell/bring a neighbor and be a part of your Community’s voice.

    As part of the planned 2024 enhancements we return to our regular monthly meeting program with our very important September 25th meeting that will feature a comprehensive panel of our Community’s Elected Officials addressing Crime, Safety and Quality of Life in our community.

    Scheduled Panelists:

    -Brad Hoylman-Sigal – State Senator

    -Brian Kavanagh – State Senator

    -Erik Bottcher – City Council

    -Carolina Rivera – City Council

    -Deborah Glick – NY State Representative

  • Weed Dispensary on the Way

    If there was any doubt about the national momentum on legalized marijuana use in America, consider this. There will be a medicinal marijuana dispensary off Union Square come January 2016. The dispensary on 14th Street between Second and Third Avenues will be run by Columbia Care, a New York City-based company that was awarded one of the state’s five licenses to open a medicinal marijuana shop. The selections were made in July, and companies are moving forward on grand openings.