Latest New School Construction Update
ByDonIn response to community concerns about the time in the evening we end our concrete placing, DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 10 more instances like this until we finish our superstructure in early June.
Therefore next week (April 2 to April 6), Superstructure work will continue at the 9th and 10th floor levels. Wednesday, April 4th, we will have an identical pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (April 9 to April 13), we will continue superstructure concrete and slabs on the 10th and 11th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, March 31st for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities.
Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
In addition to the normal work on the job site, the 14th St. Con Ed Vault utility connection street work will continue per DOT Permit granted for weekends only.
Konichiwa to Muji
ByDonMuji, the terribly chic store for minimalist (and affordable) Japanese household accessories, stationery, and casual clothing, has arrived in the neighborhood on 19th St. just west of 5th. You’ll love it.

Bye Bye Bak
ByDonBak Korean Kitchen, which shared our building on 13th St., i\s no more. It was the fifth restaurant in that location in eight years. However, the Karaoke Cave downstairs is undergoing renovation and will reopen.
Watch a Video About 12 East 13th St.
ByDonClick here
http://www.interiordesign.net/idtv/detail/768/
to see a video about the transformation of the parking garage at 12 East 13th St.Latest New School Construction Update
ByDonNext week (April 29 to May 3), material and equipment deliveries and installation work will continue on all floors inside the building. We will be work on the new sidewalks around the building as well.
The following week (May 6 to May 10), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, April 27th for interior and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City. We will also be working on Sunday as some interior work needs to be completed.
Real Estate Details That Go Deep
ByDonAnyone curious about what is happening to real estate values in our neighborhood (hint: they’re going down) should know about StreetEasy, currently the best available resource for block-by-block and apartment-by-apartment comparisons of current listings, including recent prices. An invaluable resource as we navigate these interesting economic times.