No More Crane?

According to The New School, the terrifying red crane that has been looming over us for months is scheduled for “demobilization” soon. We’ll wait and see when that actually happens.

Similar Posts

  • The New School Will Have a Sorta Green Roof

    The New School says of its upcoming building:

    “Although gardens are rare in a place as densely built as Manhattan, the designers of the University Center found room for a front lawn of sorts: On the setback between the seventh and eighth floors will sit the Green Roof, carpeted with a leafy green flower called sedum. And in true New School fashion, the Green Roof’s purpose is interdisciplinary, providing both decoration and a boost to sustainability. The sedum plantings help cool and heat the center by providing an extra layer of sustainable insulation. Further, sedum allows the roof to absorb 40 percent of the rain falling on the building, which reduces impact on the city’s water system. The Green Roof, which is just one part of an overall water conservation strategy for the University Center, will reduce the building’s potable water usage by 74 percent and sewer discharge by 89 percent.”

  • Shirley Klinghoffer Invites You to an Exhibition

     Co-op reisdent and artist Shirley Klinghoffer says:

    “Love Armor”, a nationwide collaborative art project, will be on exhibition at the Brenda Taylor Gallery, 511 W. 25th St., NYC from May 14 until June 30th. 

    The Opening Reception is on Thursday, May 14th from 6:00 – 8:00 PM.  I would love to greet my neighbors there that evening.  All are welcome!

  • Latest New School Construction Update

    Next week (October 8 to October 12), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 15 to October 19) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all upper floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.

    This weekend the site will be open on Saturday, October 6th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.

  • The Alleged New School Construction Schedule

    Here’s what they’re currently saying:

    “With demolition and abatement complete, Tishman Construction and the Durst Organization have moved on to the next major phases of the construction process: clearing and laying the foundation. Future deadlines include the following.”

    Present to August 2011: Excavation foundation

    September 2011 to May 2012: Superstructure erection

    May 2012 to October 2012: Façade and building enclosure