Latest New School Construction Update

I write to remind all that the lower 8 floors of this building are still a construction site which is regulated by the Department of Buildings. New School has heard your complaints but at this time we do not control this site. It is our hope that when we take over the building we can make some necessary changes. The University Center is a LEED building with many energy saving designs incorporated into the building so that we will be good neighbors.

Next week (December 23rd to December 27th ), material and equipment deliveries and installation work will continue on the academic floors inside the building. (Site closed on Christmas)

The following week (December 30th to January 3rd ), material and equipment deliveries and installation work will continue on academic floors (Site closed on New Year’s Day)

This weekend the site will be open on Saturday and Sunday, December 21st and 22nd for interior activities between the work hours of 7AM and 7PM as permitted by the City.

Similar Posts

  • Latest New School Construction Update

    Next week (September 16 to September 20), material and equipment deliveries and installation work will continue on the academic floors inside the building.

    The following week (September 23 to September 27), material and equipment deliveries and installation work will continue on academic floors. This weekend the site will be open on Saturday, September 14th for interior activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (January 9 to January 13), Superstructure work will continue at and 2nd , 3rd and 4th floor levels. The sidewalk shed along 14th Street has been opened and we will begin working on the side walk shed along 5th ave.

    The following week (January 16 to January 20), we will continue superstructure concrete and slabs on 2nd , 3rd and 4th floor levels. The weekend of Saturday 1/14/12 we will be installing a new crane that will service the site for the duration of the job.

    This weekend the site will be open on Saturday, January 7th, for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.