Next week (May 6 to May 10), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building and installing new curbs. Additionally we will be working on the roofs of the building.
The following week (May 13 to May 17), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, May 4th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.