Barn Joo Moves to Union Sqare West

Delicious Korean gastropub Barn Joo has relocated from a few blocks up Broadway to Union Square West and the old Heartland Brewery site. Try it out. Very tasty.

Similar Posts

  • Latest New School Construction Update

    Next week (April 22 to April 26), material and equipment deliveries and installation work will continue on all floors inside the building. We will be work on the new sidewalks around the building as well.

    The following week (April 29 to May 3), material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, April 20th for interior and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (July 2 to July 6), Mechanical equipment and work will continue at the 17th and 18th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Wednesday, July 4th, for the holiday.

    The following week (July 9 to July 13), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane is scheduled for demobilization on Saturday the 7th.

    This weekend the site will be open on Saturday, June 30th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to working on the mechanical systems of the building and using the crane and equipment to support activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Latest New School Construction Update

    Next week (June 17 to June 21), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalks around the building on 13th st. as well as taking the sidewalk shed down on 13th st. Additionally we will be working on the roofs of the building.

    The following week (June 24 to June 28), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.

    This weekend the site will be open on Saturday, June 15th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.