Update on Tammany Hall Dome Construction

Construction of the glassy turtle shell-shaped dome on top of Union Square’s landmarked Tammany Hall building is officially underway. The building at 44 Union Square, formerly home to NYC’s Democratic party machine, is being transformed into modern office and retail space. New construction photos provided to 6sqft show the start of the unconventional dome’s installation, with the diagonally intersecting glass and steel now visible from the street. The political organization of Tammany Hall formed in New York City in the late 18th century and helped Democrats control city and state politics for decades. After a few different headquarter locations, the society landed in a building on East 17th Street and Union Square. The International Ladies Garment Workers Union bought the building in 1943. Other tenants have included the New York Film Academy and the Union Square Theatre. Designed by BKSK Architects, the redevelopment project consists of a gut renovation and the addition of four stories of retail space in the building’s base, with three levels of office space on the upper levels, including inside the dome. The architects designed the glass dome as an ode to the turtle which Lenape Chief Tamanend stands upon on a Philadelphia statue. Tammany Hall was named after the leader. According to the firm, the dome is “meant to be both evocative and respectful of the building’s past while also bringing architectural spectacle to this rather staid corner of Union Square.” BKSK first submitted plans to revamp the historic building in 2014. After the project was approved a year later by the Landmarks Preservation Commission, developer Reading International secured $57.5 million in financing. Renovations began in 2016. The dome features a framework of intersecting glass and steel, manufactured by German-based firm Gartner. There’s no doubt the top floor will not only be drenched in natural light but also offer unique views of Union Square and beyond.

Similar Posts

  • Latest New School Construction Update

    Next week (May 21 to May 25), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

    The following week (May 28 to June 1), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.

    This weekend the site will be open on Saturday, May 19th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

    To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work there will be a crew on 14th st. working on the Con Ed site connections.

  • Latest New School Construction Update

    Next week (December 24 to December 28), material and equipment deliveries and installation work will continue on all floors inside the building. The site will be closed on December 25th for the holiday but will be open on Monday the 24th and Wednesday the 26th.

    The following week (December 31 to January 4), Material and equipment deliveries and installation work will continue on all floors.

    This weekend the site will be open on Saturday, December 22nd for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.