The New School says:
Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.
The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).
DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.
The NYPD 6th Precinct Community Council Meeting will take place in person Wednesday, September 25 at 7:00 PM
Our Lady of Pompeii’s Fr. Demo Hall – Lower Level at the corner of Bleecker and Carmine Streets
note: meeting will begin promptly at 7:00 pm
Please sign in at the door early if you wish to speak or ask questions of the panel.
Join the leadership of the 6th Precinct, your neighbors and local businesses for an update on community affairs. This is also your opportunity to advise Precinct Leadership of chronic or specific crime/safety/quality of life problems you see in our community so their actions are directed with your unique insights. Take this opportunity to listen or to voice your thoughts in an open and informative session. We encourage you to tell/bring a neighbor and be a part of your Community’s voice.
As part of the planned 2024 enhancements we return to our regular monthly meeting program with our very important September 25th meeting that will feature a comprehensive panel of our Community’s Elected Officials addressing Crime, Safety and Quality of Life in our community.
Scheduled Panelists:
-Brad Hoylman-Sigal – State Senator
-Brian Kavanagh – State Senator
-Erik Bottcher – City Council
-Carolina Rivera – City Council
-Deborah Glick – NY State Representative
Amazingly enough in these tough times, work is going ahead on the construction of ten floors of luxury duplex condos on the corner of 5th Ave. and 13th St, where the burned out deli once stood. To read more about the history of this spot, click here.
Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.
The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.
This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.