News

  • Latest New School Construction Update

    Next week (December 19 to December 23), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be finished this week.
    The following week (December 26 to December 30), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.
    This weekend the site will be closed on Saturday, December 17th.
    Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd.

  • Latest New School Construction Update

    Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

    The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

    This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Latest New School Construction Update

    Next week (December 5 to December 9), DOT approved street connections to underground utilities on Fifth Avenue will continue. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The following week (December 12 to December 16), we will continue superstructure concrete and slabs. Street utility connection work will continue.

    This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (November 21 to November 25), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25 and 11/26, weather pending. The following week (November 28 to December 2), we will continue superstructure concrete and slabs. Street utility connection work will continue.

  • Lastest New School Construction Update

    Next week (November 14 to November 18), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A street crane will be moved into position early on Wednesday the 11/16 on 13th street to place structural steel in the building and should be out by the end of the day, weather pending.

    The following week (November 21 to November 25), we will continue superstructure concrete and slabs. Street utility connection work will continue. Sidewalk sheds will continue being erected around the perimeter of the site. The project will be closed on Thanksgiving Day, 11/24, and open for work on 11/25.

    This weekend the site will be open on Saturday, November 12th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

  • Latest New School Update

    Next week (November 7 to November 11), DOT approved street connections to underground utilities on Fifth Avenue and 13th street will continue. Superstructure work will continue at cellar, 1st, and 2nd floor levels. A sidewalk shed will be erected around the perimeter of the site.

    The following week (November 14 to November 18), we will continue superstructure concrete and slabs. Street utility connection work will continue. A street crane will be moved into position on 13th street to place structural steel in the building.

    This weekend the site will be open on Saturday, November 5th for superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, and rebar for concrete placement and use of the crane and equipment to support all activities.

  • Latest New School Update

    Next week (October 31 to November 4), Contractors will finish excavating and loading out material. Concrete foundation walls and slab on grade work will conclude as well as underground electrical and plumbing work. DOT approved street connections to underground utilities on Fifth Avenue will progress. Superstructure work will continue at cellar, 1st, and 2nd floor levels.

    The following week (November 7 to November 11), we will continue superstructure concrete and slabs. Street utility connection work will continue. A sidewalk shed will be erected around the perimeter of the site, subject to DOB approval, to protect pedestrians from superstructure work.

    This weekend the site will be open on Saturday, October 29 for foundation and superstructure related activities between the work hours of 9AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, waterproofing and rebar for concrete placement and use of the crane and equipment to support all activities. We may pour a section of slab on grade concrete on Saturday. There will be no rock excavation or rock chopping.

  • Latest New School Construction Update

    Next week (October 10 to October 14), contractors will continue to excavate earth and load out material. Concrete foundation walls at the South East corner of the site and slab on grade work will continue. Underground electrical and plumbing work will continue. DOT approved street connections to underground utilities on Fifth Avenue will progress. Formwork and rebar for superstructure will continue at cellar levels.

    The following week (October 17 to October 21 ), we will continue superstructure concrete and slabs, street utility connections and underground electrical and plumbing.