Month: February 2013

  • Latest New School Construction Update

    Next week, 03/04/2013 – 03/08/2013 Material and equipment deliveries and installation work will continue on all floors inside the building. Roof work, work on the new sidewalks around the building, and the dismantling of the construction hoist on the building exterior will also continue.

    The following week, 03/11/2013 – 03/15/2013 Material and equipment deliveries and installation work will continue on all floors and roofs. Sidewalk work and dismantling of the construction hoist on the building exterior will also continue.

    We anticipate the take down of the 14th Street sidewalk shed to begin within the next 2 weeks.

  • Latest New School Construction Update

    Next week (February 25 to March 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. We have begun dismantling the construction hoist on the building exterior and will continue to do so for the upcoming weeks.

    The following week (March 4 to March 8), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

    This weekend the site will be open on Saturday, February 23rd for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.

  • Latest New School Construction Update

    Next week (February 18 to February 22), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The sidewalk shed on 14th st. is scheduled to begin dismantling, pending construction progress. The site will be closed on Monday, February 18th, for the holiday.

    The following week (February 25 to March 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

  • Latest New School Construction Update

    Next week (February 11 to February 15), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

    The following week (February 18 to February 22), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. The site will be closed on Monday, February 18th, for the holiday.

    This weekend the site will be open on Saturday, February 9th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.