December 2011

You are currently browsing the monthly archive for December 2011.

Looking ahead to the upcoming holiday, the New School construction site will be closed on Saturday, December 31st and also on Monday, January 2nd. Next week (January 2 to January 6), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site and we will be opening the one on 14th st. The following week (January 9 to January 13), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels. In the upcoming weekend, January 14th, we plan on installing the new crane on Fifth Avenue.

Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd. Next week (December 26 to December 30), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard is finished.The following week (January 2 to January 6), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.

Next week (December 19 to December 23), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be finished this week.
The following week (December 26 to December 30), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.
This weekend the site will be closed on Saturday, December 17th.
Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd.

Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.