    The former East West Bookstore on 5th Ave between 13th and `14th will soon open as Human Food, an upscale takeout place with vegan and “paleo” offerings.

  • Latest New School Construction Update

    Next week (October 1 to October 5), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 8 to October 12) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.

    This weekend the site will be open on Saturday, September 29th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working in the street at 14th Street and 5 Avenue.

  • Latest New School Construction Update

    Next week (September 24 to September 28), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on the upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.

    The following week (October 1 to October 5) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.

    This weekend the site will be open on Saturday, September 22nd for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

  • Latest New School Construction Update

    Next week (September 17 to September 21), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. To aid in the installation of the lower level curtain wall a crane will be arriving on site Monday, the 17th. The crane will be inside the construction perimeter and will not affect pedestrian or automotive traffic.

    The following week (September 17 to September 21) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    This weekend the site will be open on Saturday, September 15th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

  • Latest New School Construction Update

    Next week (September 10 to September 14), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    The following week (September 17 to September 21) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    This weekend the site will be open on Saturday, September 8th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.