  • Latest New School Construction Update

    Next week (September 17 to September 21), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. To aid in the installation of the lower level curtain wall a crane will be arriving on site Monday, the 17th. The crane will be inside the construction perimeter and will not affect pedestrian or automotive traffic.

    The following week (September 17 to September 21) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    This weekend the site will be open on Saturday, September 15th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

  • Latest New School Construction Update

    Next week (September 10 to September 14), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    The following week (September 17 to September 21) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site.

    This weekend the site will be open on Saturday, September 8th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed is on site working on the building but is not in any of the streets.

  • Glaze Opens

    Glaze Teriyaki Grill has opened up near Union Square. Their signature teriyaki entrees ($6.75 to $9.50) include chargrilled chicken thigh or breast, Japanese BBQ hanger steak, fresh-never-frozen organic salmon, boneless pork loin, wok vegetables or soy marinated tofu. It’s on 4th Ave. between 13th and 14th.

  • Bye Bye Bak

    Bak Korean Kitchen, which shared our building on 13th St., i\s no more. It was the fifth restaurant in that location in eight years. However, the Karaoke Cave downstairs is undergoing renovation and will reopen.

  • Latest New School Construction Update

    Next week (August 20 to August 24), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will continue on 13th st. with the aid of a small crane. The crane will remain on 13th st. for the purpose of curtain wall installation.

    The following week (August 27 to August 31) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Work on 13th st should be complete by the end of this week and will be moved to 5th ave. to continue wrapping the building.

    This weekend the site will be open on Saturday, August 25th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. The crane on 13th st. will not be used during the weekend. Con Ed is on site working on the building but is not in any of the streets.

    Additionally over the holiday weekend the site will be open on Saturday, September 1st but will be closed on Monday, the 3rd.

  • Latest New School Construction Update

    This weekend the site will be open on Saturday, July 28st for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. The crane on 13th st. will not be used during the weekend.

    Next week (July 30 to August 3), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue and lower levels will continue on 13th st. with the aid of a small crane. The crane will remain on 13th st. for the purpose of curtain wall installation.

    The following week (August 6 to August 10) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors.