Next week (January 16 to January 20), Superstructure work will continue at and 3rd, 4th and 5th floor levels. Sidewalk shed along 14th Street has been opened and we will open the sidewalk shed along 5th ave completing the sidewalk shed work.
The following week (January 23 to January 27), we will continue superstructure concrete and slabs on 3rd, 4th and 5th floor levels.
This weekend the site will be open on Saturday, January 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

In addition to the normal work this Saturday we will be installing a new crane on 5th Ave. that will service the site for the duration of the project. During the installation 13th St. will be closed as well as some lanes on 5th Ave.

Now Open: Aesop

On University near 10th…the most expensive personal grooming products on Earth.

The closing of The Adore is a real loss to the block. Here’s a great article on the history of that fascinating little building. Rumored to come next: a high-end cocktail lounge.

On University Place a few blocks down. And it appears to be very popular. Good desserts.

Next week (January 9 to January 13), Superstructure work will continue at and 2nd , 3rd and 4th floor levels. The sidewalk shed along 14th Street has been opened and we will begin working on the side walk shed along 5th ave.

The following week (January 16 to January 20), we will continue superstructure concrete and slabs on 2nd , 3rd and 4th floor levels. The weekend of Saturday 1/14/12 we will be installing a new crane that will service the site for the duration of the job.

This weekend the site will be open on Saturday, January 7th, for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Looking ahead to the upcoming holiday, the New School construction site will be closed on Saturday, December 31st and also on Monday, January 2nd. Next week (January 2 to January 6), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site and we will be opening the one on 14th st. The following week (January 9 to January 13), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels. In the upcoming weekend, January 14th, we plan on installing the new crane on Fifth Avenue.

Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd. Next week (December 26 to December 30), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard is finished.The following week (January 2 to January 6), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.

Next week (December 19 to December 23), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be finished this week.
The following week (December 26 to December 30), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.
This weekend the site will be closed on Saturday, December 17th.
Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd.

Next week (December 12 to December 16), DOT approved street connections to underground utilities on Fifth Avenue have been completed. Superstructure work will continue at 1st and 2nd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be started this week as well.

The following week (December 19 to December 23), we will continue superstructure concrete and slabs on 1st and 2nd floor levels.

This weekend the site will be open on Saturday, December 3rd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork, plumbing and electrical work, rebar for concrete placement and use of the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.

Corkbuzz Is Open

Our downstairs neighbor Corkbuzz is now open. Read about it here.

 